Building regulation
(extract)

 
Detailed rules of territories meant for building
Living areas for build-up

1., The living belt is according to the particular usage:
     a, country-like (FAL)
     b, greenbelt (KL)

2., The division of the living areas contains the project of the regulation.

3., This living area has characteristically few population. Outside of the built-up lots has the region agriculturally utilized areas too, and serve for placing of farming- and forestry buildings. The territory can be built-up by order of paragraphes number 14. and 32. of OTÉK.

4., (...)

5., Living area in green belt (KEL) can be established and built-up as following:
Fixed building characteristics:

Codes of buildingbelt KEL- O/30/0,6
4,5/550-15/50
Way of the build-up
Building-up (%)
Levelconsistence
Height limit of building (m)
Building site(m2)
Plot width(m)
Green area (%)
standing on the sideline
max.:30
max.:0,6
max.:4,5
min.:550
min.:15
min.:50

The instruction used on plansheet of regulation, regarding to the area is variable for freestanding building-up method, if there isn't any violation of other law applying to developing and building-up.

6., Inside of the living area can be established garage, storage, retail shop, workshop, atelier, cellar, press-house, place for animals, granary, barn. The groundterritory of the place for animals can be maximum 10% of the buildingsite territory, by built-in regulation. Place for animals can be built only to one's own needs, for domestic small animals.

7., There can be established garden building, greenhouse, subgrade building, waste basin, display case, connection of public service, place for firing, icepit.

8., In the newly developed living area is the maximum height of building 4,5 m, or has to be taken into consideration the already existing height.
Attic can be built-in.
Buildings are allowed to build by the prescribed order with minimum 30, maximum 45 grade angle of pitch and tiling in scaled way. Mainbuildings are allowed to build only parallel or perpendicular crest to the street. In case of parallel crest, gable and firewall can't be built on side of neighbours.

9., The conditions of the issue of the construction permit is the beginning the operations of public utilities and the issue of the permit of use is the conserning rate of the public services: potable water, elektricity, drains.

10., It has to be taken into consideration the signed building line for establishing houses in the building area, in lack of it can be applied the rule, 35 paragr. of OTÉK, or adapted to the existing building-up.